ACTIVITYSTART DATEEND DATE
Secure construction site/fencing11.29.2412.1.24
Enabling work12.2.241.3.25
Demolition of Allen Center1.3.254.25.25
Caissons and Sheet Piling5.9.257.14.25
Building Construction10.15.255.4.27
Project Completion6.11.27