The Kellogg Education Center (formerly Allen Center)
construction project timeline
ACTIVITY | START DATE | END DATE |
Secure construction site/fencing | 11.29.24 | 12.1.24 |
Enabling work | 12.2.24 | 1.3.25 |
Demolition of Allen Center | 1.3.25 | 4.25.25 |
Caissons and Sheet Piling | 5.9.25 | 7.14.25 |
Building Construction | 10.15.25 | 5.4.27 |
Project Completion | 6.11.27 |